Housing Provision

Dáil Éireann Debate, Thursday - 15 June 2023

Thursday, 15 June 2023

Ceisteanna (224)

Bernard Durkan

Ceist:

224. Deputy Bernard J. Durkan asked the Minister for Housing, Local Government and Heritage the status of the stage 4 approval process to select a contractor to build 38 new homes on (details supplied); how long the tender process has been ongoing and when he anticipates stage 4 approval being granted; and if he will make a statement on the matter. [29026/23]

Amharc ar fhreagra

Freagraí scríofa

I am advised by Dublin City Council that work continues on this project. Stage 3 Pre-tender Approval was awarded by my Department on the 26 May 2022.

I am advised by the Council that this Project is the initial seed project for the establishment of Multi-Party Framework Agreements for Residential Works Projects for Dublin City Council.

The project works were tendered under the Restricted Procedure, which is a two stage process. Final tenders were returned on 17 May 2023. The evaluation of those tenders under the Most Economically Advantageous Tender (MEAT) criteria is currently in progress.

Following that process my Department anticipates a Stage 4 submission from Dublin City Council.