Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Refurbishment

Dáil Éireann Debate, Tuesday - 25 July 2023

Tuesday, 25 July 2023

Ceisteanna (473)

Darren O'Rourke

Ceist:

473. Deputy Darren O'Rourke asked the Minister for Education when refurbishment works at a school (details supplied) will be completed; and the estimated cost of these works. [36528/23]

Amharc ar fhreagra

Freagraí scríofa

I am pleased to advise that the large scale major building project for the school referred to by the Deputy was approved to construction earlier this year. The project is devolved for delivery to Louth and Meath Education and Training Board (LMETB).

My Department understands from LMETB that the project commenced on-site in May of this year and completion is expected towards the end of 2025. The overall cost of the project will not be finalised until the project is completed and final accounts have been paid.

Barr
Roinn