474. Deputy Darren O'Rourke asked the Minister for Education when refurbishment works at a school (details supplied) will be completed; and the estimated cost of these works. [36529/23]

Amharc ar fhreagra

Freagraí scríofa

The large scale capital project at the school referred to by the deputy is part of an educational campus project with a post-primary school.  The project commenced on site in August 2022 with an expected completion date in Q2 2025.