Schools Building Projects

Dáil Éireann Debate, Thursday - 29 February 2024

Thursday, 29 February 2024

Ceisteanna (180, 181, 182)

Michael Ring

Ceist:

180. Deputy Michael Ring asked the Minister for Education the update position with an extension for a school in County Mayo (details supplied); and if she will make a statement on the matter. [9772/24]

Amharc ar fhreagra

Michael Ring

Ceist:

181. Deputy Michael Ring asked the Minister for Education when a final decision will be made on an extension for a school in County Mayo (details supplied); and if she will make a statement on the matter. [9774/24]

Amharc ar fhreagra

Michael Ring

Ceist:

182. Deputy Michael Ring asked the Minister for Education when an application for an extension for a school in County Mayo (details supplied) was first made; when was this application assessed; what stage is this at now; and if she will make a statement on the matter. [9775/24]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 180, 181 and 182 together.

The school referred to by the Deputy has been approved a project under my Department’s Additional School Accommodation (ASA) Scheme to provide 6 general classrooms (prefab replacement), 4 SET rooms, 1 textiles room, 2 classroom SEN base and ancillary, removal of prefabs,  and replacement works. 

The project has been devolved to the school authority for delivery.    

My Department has received the Stage 1 report submitted by the design team and this is currently under review by my Department's Professional and Technical staff.   

Once the review is complete, the outcome will be communicated to the school authority in due course on the next steps to progress this important project.

Question No. 181 answered with Question No. 180.
Question No. 182 answered with Question No. 180.