Ceisteanna—Questions. Oral Answers. - Concrete Runways at Collinstown.

asked the Minister for Industry and Commerce if he will state the reason for the delay in carrying out the proposed £300,000 contract for the construction of concrete runways at Collinstown Airport.

The delay in placing this contract has been due to a decision taken in July to adopt a three-runway layout instead of the four-runway layout specified in the invitation for tenders. Radical alterations have been made in the contract plans and specifications, involving protracted negotiations with the prospective contractor.

When are you going to get the job done?

Can the Minister say if the work will be put in hands shortly?

I hope it will be begun shortly.