Schools Building Projects Data

Dáil Éireann Debate, Monday - 11 September 2017

Monday, 11 September 2017

Ceisteanna (436)

Brendan Smith

Ceist:

436. Deputy Brendan Smith asked the Minister for Education and Skills further to Parliamentary Question No. 10 of 6 July 2017, if a building project at a school (details supplied) will proceed to construction stage at an early date; and if he will make a statement on the matter. [38600/17]

Amharc ar fhreagra

Freagraí scríofa

The Stage 2(b) Detailed Design Report for the major building project at the school to which the Deputy refers has recently been reviewed by my Department and comments on the report issued to the Board of Management in July 2017. A response to these comments is awaited from the Board of Management and its Design Team.

In parallel, the Board of Management and its Design Team are currently finalising the assessment of suitably qualified contractors to which the project can be tendered.

Once these steps are finalised my Department will then revert to the school with a timeframe to proceed to tender and construction stage.